This case related to a development of 4 blocks of waterfront properties in Greenwich/Deptford.

United KingdomLitigation, Mediation & Arbitration

Ampurius Nu Homes Holdings Limited v Telford Homes (Creekside) Limited [2012] EWHC1820 (Ch)

This case related to a development of 4 blocks of waterfront properties in Greenwich/Deptford. The parties entered into an agreement under which Telford agreed to construct the mixed use blocks and grant long leases of the commercial units to Ampurius. In March 2009 Telford stopped work on 2 of the blocks because of funding difficulties. In November 2009, Ampurius alleged that cessation of work amounted to a repudiatory breach. In October 2010, Ampurius' solicitors gave notice terminating the contract for repudiatory breach. By that stage, Telford had just recommenced work, so it denied being in repudiatory breach and terminated the contract itself for Ampurius' repudiatory breach.