ARTICLE · 24 FEBRUARY 2009

CMA CGM SA v HYUNDAI MIPO DOCKYARD CO. LTD [2008] EWHC 2791 (Comm) – Arbitration vs Brussels Regulation

HMD and ERS entered into 4 shipbuilding contracts under which HMD would build 4 container vessels for ERS.

United KingdomLitigation, Mediation & Arbitration

HMD and ERS entered into 4 shipbuilding contracts under which HMD would build 4 container vessels for ERS. The 4 contracts were identical in their material clauses, all of which provided for London arbitration and required either party seeking to transfer its rights and obligations under the contract to a third party to obtain the prior consent of the other party, such consent not to be unreasonably withheld.

CMA wanted to take over the contracts from ERS but HMD refused to agree to a novation. CMA therefore sued HMD in tort in French proceedings, alleging HMD was unreasonably withholding its consent in breach of the relevant article under the French Civil Code. During these proceedings, the parties finally came to agreement over the novations and a separate novation took place in respect of each shipbuilding contract. These novations however did not take effect until after the construction work on the vessels had been completed, as identified by a particular Transfer

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from