A discussion on a recent case, where the High Court departed from the normal costs rules that follow an offer to settle intended to have the costs consequences associated with Part 36 of the Civil Procedure Rules.

United KingdomLitigation, Mediation & Arbitration

Pre-action Protocol – a cautious reminder about compliance

Webb Resolutions Ltd v Waller Needham & Green (a firm) [2012] EWHC 3529

Facts

In this case, the High Court departed from the normal costs rules that follow an offer to settle intended to have the costs consequences associated with Part 36 of the Civil Procedure Rules. The usual order is that the claimant will be entitled to recover its costs incurred beginning from the expiry of the relevant period (21 days after the offer was made) to the date that the offer was accepted. However, the Court departed from this usual position citing the claimant's non-compliance with the relevant pre-action protocol.

The defendant accepted a Part 36 offer a year after it was made on the basis that the offer could not properly be assessed before then as a result of the claimant's failure to deal with the Professional Negligence Pre-action Protocol – the claimant had not complied with the defendant's request for

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.