Commercial Court Rules On Buyers’ Rights To Extensions Of Time Under GAFTA 49

This recent decision from the Commercial Court provides useful guidance on the construction of Clause 8 of the popular GAFTA 49 form; in particular, on the nature and scope of a buyer’s right to extend the delivery period under that clause.

United KingdomInternational Law

Nidera BV v. Venus International Free Zone for Trading and Marine Services SAE (Pioneer Wave) [2014] EWHC 2013 (Comm)

This recent decision from the Commercial Court provides useful guidance on the construction of Clause 8 of the popular GAFTA 49 form; in particular, on the nature and scope of a buyer's right to extend the delivery period under that clause.

The Court held that the "clear and unqualified" words in Clause 8 mean that a buyer has an absolute right to extend the shipment period under Clause 8 of GAFTA 49, and the right would remain available to a buyer whose nominated vessel had already arrived and was presented within the delivery period.

The background facts

In late 2010, Venus ("Buyers") bought 30,000 mt of Ukrainian yellow corn from Nidera ("Sellers") on FOB terms, using the GAFTA 49 standard form contract with delivery 16-31 October. The Buyers nominated a vessel that tendered NOR at the load port, Yuzhny, Ukraine, on 15 October 2010.