Introduction
The majority of ships continue to be built in the shipyards of
China, Korea and Japan. Where foreign buyers are involved, these
contracts are usually subject to English law and, in the event of a
dispute, arbitration. From a buyer's perspective, getting the
timing right for starting proceedings and pursuing them quickly can
be crucial, particularly for pre-delivery disputes and those under
Chinese refund guarantees.
Timing pitfall of Chinese refund guarantees
Care also must be taken with timing when looking to recover
instalments under a refund guarantee, particularly if it has been
issued by a Chinese bank. Generally such payment will be suspended
if arbitration proceedings are commenced within 28 days of the
request for payment. The refund guarantee is an important document
in the context of shipbuilding contracts since title to the vessel
usually remains with the shipyard until delivery, although
instalments are paid at various stages during