Today's entry is an explanation of how the government
is intending to implement the infrastructure planning reforms
announced on 6 September.
I have learnt from officials at the Department of Communities
and Local Government (CLG) that the implementation of the
announcements made on 6 September is taking shape and consists of
four workstreams. The written ministerial statement by
Eric Pickles is here and the Number 10
news release is here.
The key paragraph in the statement is quite far down and is as
follows:
"... we now intend to review the thresholds for some of
the existing categories in the regime, and also to bring new
categories of commercial and business development into the regime -
making it possible for such schemes, where they are of sufficient
significance, to be considered and determined at a national level.
We will also work to extend the principle of a one-stop-shop for
non-planning consents for major infrastructure, and amend the
Special