Summary
On 16 December 2021, the PFI Centre of Excellence issued its
Phase 1 PFI Expiry Health and Learnings Report. In this BCLP
Insight, Jennifer Varley considers how these development areas may
impact both the public and private sector.
On 16 December 2021, the PFI Centre of Excellence within the
Infrastructure and Project Authority
(“IPA”) issued its
Phase 1 PFI Expiry Health and Learnings Report.
The report confirms that following its ‘health
check' of 52 projects that are due to expire before the end
of 2027, more than half of the projects need either critical, major
or moderate additional work to be ready for handover and exit and
only 5 projects were deemed to be ‘at target
readiness'. It then identifies key areas for further
development.