The latest Technology and Construction Court (TCC) judgment on payment and the enforcement of an adjudicator's decision has just been handed down, and has some key lessons, particularly in the current

United KingdomFinance and Banking

The latest Technology and Construction Court (TCC) judgment on payment and the enforcement of an adjudicator's decision has just been handed down, and has some key lessons, particularly in the current crisis.

We analyse the decision in Broseley (London) Ltd v Prime Asset Management Ltd [2020] and the significant issues covered in relation to adjudication enforcement and the resolution of final accounts.

Background

  • PAML appointed Broseley to carry out refurbishment works for PAML at Stanley House in Chelsea under a construction contract (the Contract) governed by the Housing Grants, Construction and Regeneration Act 1996 as amended (the Construction Act). The works were commenced in December 2017.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from