ARTICLE · 07 SEPTEMBER 2017

Robin Rigg Supreme Court Decision

Why complying with an agreed international standard can still land you in stormy waters.

United KingdomEnergy and Natural Resources

Why complying with an agreed international standard can still land you in stormy waters.

In a decision that may come as a shock to many, and that will have potentially wide-reaching ramifications for English law contracts, the UK Supreme Court has overturned the Court of Appeal's decision in the long-running Robin Rigg offshore wind farm dispute, by finding in favour of E.ON Climate & Renewables (E.ON).

This decision could significantly affect the risk assessment of existing contracts, as well as insurance and finance arrangements, in the offshore wind farm sector and beyond.

In its judgment, the Supreme Court has held that:

  • In giving effect to the natural meaning of the words used by the parties, the contractor, MT Højgaard (MTH), was under an obligation to ensure that the foundations at Robin Rigg would have a minimum lifetime of 20 years.