Share on LinkedInShare on LinkedIn

ARTICLE · 16 JULY 2007

"Total Cost" Claim Fails

In the recent case of Petromec, the Commercial Court refused to permit the claimant to proceed with its "total cost" claim.

United KingdomCorporate/Commercial Law

In the recent case of Petromec, the Commercial Court refused to permit the claimant to proceed with its "total cost" claim.

What is a "total cost" claim?

It is a claim for additional payment, where the amount claimed represents the difference between the contractor’s actual cost (plus profit margin) and the contract price for the work in question. "Total cost" claims involve rolling up a number of heads of claim into a single claim. E.g. if a contractor is given 120 variation instructions, which have the effect of increasing its overall volume of work, the contractor may attempt to make a single claim for its increased cost arising from the variations, rather than making 120 individual variation claims. Claims are often expressed as "total cost" claims because it is difficult (or perhaps impossible) to demonstrate how each individual matter (e.g. each individual variation instruction) caused a contractor’s costs to increase.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from