ARTICLE · 22 NOVEMBER 2017

The Devil Is In Paragraph 3.2.2.2 (ii)

Travers Smith LLP
Travers Smith LLP
Contributor
Travers Smith LLP

Travers Smith LLP

It is not just law at Travers Smith. We treat our clients’ business as our business, their dispute...

View firm profile
Explore more from Travers Smith LLP

What if the main body of a contract appears to say one thing, but the detailed wording of a technical schedule appears to be at odds with that?

United KingdomCorporate/Commercial Law

The importance of consistency throughout a contract

What if the main body of a contract appears to say one thing, but the detailed wording of a technical schedule appears to be at odds with that? You might have thought that the main body of the contract would take precedence – but a recent Supreme Court ruling suggests otherwise. And in terms of how to respond, the case is likely to create difficulties for both suppliers and customers.

Turbine trouble

MT Hojgaard v E.ON Climate & Renewables (2017) concerned a dispute over the failure of offshore wind turbines installed by MT Hojgaard. The purchaser, E.ON, argued that the foundations of the turbines were effectively subject to a 20 year warranty set out in paragraph 3.2.2.2 (ii) of the Technical Requirements of the project (which formed part of the agreement).