ARTICLE · 17 AUGUST 2018
Providing For Concurrent Delay: Contract Provision Trumps Common Law Principle

Shepherd and Wedderburn
Contributor

Shepherd and Wedderburn
We are an independent law firm, headquartered in Scotland, delivering high-quality legal advice and...
View firm profileIn North Midland Building Ltd v Cyden Homes Ltd, the Court of Appeal held that an express contractual term allowing an employer to levy liquidated damages for periods of concurrent delay