Delictual Action For Damages – Claining For Loss Of Profit In The Case Of An Unsuccessful Tender

The rules of being awarded a contract by way of a tender process are encapsulated in Section 217(1) of the Constitution, which indicates that when an organ of state contracts for goods and services, it must do so in accordance with ...

South AfricaReal Estate and Construction

The rules of being awarded a contract by way of a tender process are encapsulated in Section 217(1) of the Constitution, which indicates that when an organ of state contracts for goods and services, it must do so in accordance with principles of fairness, equitability, transparency, competitiveness and cost-effectiveness. On 24 June 2021, the Court delivered a judgment in the case of Esorfranki (Pty) Ltd v Mopani District Municipality [2021] JOL 50619 (SCA) (reportable case no 916/2018, 24-6-2021) (the "Esorfranki case"), which dealt with the claim for delictual damages for loss of profits by an unsuccessful tender applicant.

Case Overview

In August 2010, the Mopani District Municipality ("Respondent") started the bidding process for tenders for the construction of concrete reservoirs, and a water pipeline between the Nandoni dam in Thohoyandou and Nsami water treatment works based in Giyani in Limpopo. The Respondent awarded the contract to Tlong Re Yeng CC and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from