The DMRE's RFI In Respect Of The Design Of A Risk Mitigation Power Purchase Programme

The Department of Mineral Resources and Energy (the "Department") intends to launch a Risk Mitigation Power Purchase Programme ("RMPPP") to alleviate the current electricity...

South AfricaGovernment, Public Sector
  • The Department of Mineral Resources and Energy (the “Department”) intends to launch a Risk Mitigation Power Purchase Programme (“RMPPP”) to alleviate the current electricity supply constraints in the immediate to medium-term. This is as envisaged in the Integrated Resource Plan promulgated in October 2019.
  • On 13 December 2019, the Department issued a request for information in respect of the design of a RMPPP (the “RFI”). The objective of the RFI is, amongst other things, to enable the Department to:
    • consider the various options available to procure power generation capacity that can be connected to the grid as expeditiously as possible and at the least possible cost; and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from