The dispute resolution terms of engineering contracts can cause
problems. An example is the recent case of Tubular Holdings (Pty)
Ltd v DBT Technologies (Pty) Ltd, an unreported decision of South
Gauteng High Court.
DBT Technologies – a subcontractor to Eskom in the
Kusile Project – further contracted to Tubular Holdings in a
deal worth some R1.3 billion. ContractFIDIC's clause 20
governs the dispute resolution procedure.
Clause 20.4(4) of FIDIC provides that the decision of the
Dispute Adjudication Board (DAB) shall be binding on both parties,
who 'shall promptly give effect to it unless and until it shall
be revised in an amicable settlement or an arbitral award'.
Clause 20.4(5) provides that if either party is dissatisfied with
the DAB's decision it can give a notice of dissatisfaction
within 28 days. Clause 20.4(7) says that a DAB decision
becomes final and binding if neither party files a notice of
dissatisfaction within the 28-day period. And Clause