On May 29, 2025, President Bola Ahmed Tinubu signed the Nigerian
Upstream Petroleum Operations (Cost Efficiency Incentives) Order,
2025 (the "Order"), which has a retroactive commencement
date of April 30, 2025. This Order aims to tackle one of the most
persistent challenges in the upstream sector: excessive and
inefficient operating costs.
Nigeria's upstream operations have faced issues such as
production delays, political interference, inefficient workflows,
fiscally negligent procurement processes, amongst others, all of
which contribute to rising operating costs. Rather than imposing
punitive measures, the Order introduces a performance-based
incentive regime. Under this framework, companies that can
demonstrate cost-effective operations by meeting or spending below
the benchmark Unit Operating Costs ("UOC") set annually
by the Nigeria Upstream Petroleum Regulatory Commission
("NUPRC") will be rewarded with tax credits. This
newsletter outlines