On December 07, 2017, SENER announced the call for a bidding process for the finance, installation, maintenance, management and operation of the Baja California Interconnection System...

MexicoEnergy and Natural Resources

On December 07, 2017, the Ministry of Energy ("SENER") announced the call for a bidding process for the finance, installation, maintenance, management and operation of the Baja California Interconnection System (BC) with the National Interconnected System (SIN), which would represent the first electrical energy transmission project with private participation (the "Project").

The Project will consist in two converter stations and one direct high-voltage transmission line with an estimated length of 1,400 circuit kilometers with a tension level of +/- 500 kilo volts and a transmission capacity of 1,500 MW.

Pursuant to the information released by SENER, the proposed calendar for the 1st SENER tender would be as follows: