Planning Issues In Energy Projects Relying On Section 5 Declarations

Mason Hayes & Curran LLP
Contributor

Mason Hayes & Curran LLP
Managing Partner: Will Carmody Chair: Philip Nolan Number of partners: 124 Languages: French,...
View firm profileIn O'Grianna & Ors. v An Bord Pleanála [2014] IEHC 632 23, the High Court held that a project could not, for planning purposes, lawfully be split into two independent parts – the wind farm and the grid connection.