In O'Grianna & Ors. v An Bord Pleanála [2014] IEHC 632 23, the High Court held that a project could not, for planning purposes, lawfully be split into two independent parts – the wind farm and the grid connection.

IrelandReal Estate and Construction

In O’Grianna & Ors. v  An Bord Pleanála [2014] IEHC 632 23, the High Court held that a project could not, for planning purposes, lawfully be split into two independent parts – the wind farm and the grid connection. The Kilronan case, Daly v Kilronan Windfarm Ltd [2017] IEHC 308, raised a different question: where permission exists for the wind farm, can the grid connection works be exempt under statute? If so, how does this affect existing projects and those in development without planning permission for their grid connection relying on existing Section 5 declarations?

Section 5

Any person may request a declaration from a planning authority as to whether any development is or is not exempted development under section 5 of the Planning and Development Act, 2000 (“Section 5”). This is an optional procedure. There is no requirement to seek a declaration, as a matter of law the development is either exempted development, i.e. does not require planning permission,