CRU Builds Upon The Reduced Planning Permission Requirements For RED III Projects

William Fry LLP
William Fry LLP
Contributor
William Fry LLP

William Fry LLP

William Fry advises leading Irish and international companies, covering both the public and private...

View firm profile
Explore more from William Fry LLP

As with the ECP-GSS (which we reviewed here), the Proposed Decision applies to onshore projects seeking connection to the electricity system.

IrelandReal Estate and Construction

As with the ECP-GSS (which we reviewed here), the Proposed Decision applies to onshore projects seeking connection to the electricity system.

It does not apply to interconnectors, demand connections, micro-generation, or offshore electricity connections.

Pre-Engagement Process

Per the ECP-GSS, before submitting its grid connection application, a RED III Project (i.e. renewable projects and co-located energy storage projects) must enter into a 'pre-engagement process' with the relevant SO in which the SO undertakes a 'high-level technical assessment' of the project. Grid connection applications may then be submitted prior to the planning permission being granted, once the relevant project's planning application has been acknowledged as complete by the relevant planning authority.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from