ARTICLE · 17 AUGUST 2018

Tick-Tock: Baker J. Provides Fresh Analysis On Time Limits For Procurement Challenges

To understand this case it is necessary to set out the timelines in a bit of detail

IrelandGovernment, Public Sector

On 21 June 2018, Baker J. analysed the nature of the time limits applicable to the judicial review of public contracts in Newbridge Tyre & Battery Company Ltd. v. Garda Commissioner [2017] 964 JR. This is an important case which provides fresh analysis on the critical issue of time AARON BOYLE limits for public procurement challenges.

BACKGROUND

To understand this case it is necessary to set out the timelines in a bit of detail. On 22 June 2017 An Garda Síochána commenced a competition to procure garage services for vehicles kept by An Garda Síochána which were either damaged as a result of traffic collisions or seized and stored for further criminal investigation. Tenderers were informed of the outcome of the competition by letter dated 27 October 2017. Corcoran Autobody Works Limited ("Corcoran") was identified as the preferred bidder. On the same date, Corcoran's competitor, Newbridge Tyre and Battery Co Limited ("Newbridge"), wrote to An Garda Síochána

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from