The Future Of Data Centres In Ireland

Addleshaw Goddard
Addleshaw Goddard
Contributor
Addleshaw Goddard

Addleshaw Goddard

Addleshaw Goddard is a global law firm trusted by over 3,000 major organisations, including 51 FTSE...

View firm profile
Explore more from Addleshaw Goddard

Data centre development has become a significant industry in Ireland over the last decade. In this article, we look at the main challenges faced by the industry and the ways in which these challenges are being addressed.

IrelandEnergy and Natural Resources

Data centre development has become a significant industry in Ireland over the last decade. In this article, we look at the main challenges faced by the industry and the ways in which these challenges are being addressed.

Industry Challenges and Changes to Come

1. What are the challenges I might face when trying to a develop data centre in Ireland?

  • Power Supply: The greatest challenge facing data centre developers in Ireland is accessing power. Dublin established itself as a global data centre hub through a 10-to-15-year period of rapid data centre development. However, a lack of investment in the national electricity grid during this time, means that industry demand currently far outstrips power supply. In 2021, the Commission for Regulation of Utilities (CRU) slowed the rate of data centre development by publishing a formal Direction, introducing strict criteria for connecting data centres to the grid. We are now seeing change in this area as, earlier

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from