ARTICLE · 26 MARCH 2018

Legal Update: Key Environmental And Planning Matters For The Wind Energy Sector

Changes in the planning landscape for wind farm developments continue, with a number of important decisions having been delivered by the High Court, Supreme Court...

IrelandEnergy and Natural Resources

Changes in the planning landscape for wind farm developments continue, with a number of important decisions having been delivered by the High Court, Supreme Court and Court of Justice of the European Union ("CJEU")within the past few months. This note outlines the key takeaways from these decisions.

PRE-PLANNING CONSIDERATIONS

The following recent decisions provide additional guidance to developers on the content of their planning application documents.

Site Notice

The decision of the High Court in Alen-Buckley v An Bord Pleanála1 addressed what is considered to be adequate information to be contained on a site notice. The Applicants in Alen-Buckley argued that the site notice (a) did not contain sufficient information relating to the grid connection and haul route works and (b) it did not state the blade length and rotor diameter of the turbines.