The CRU has published its decision paper on the grid access pathway for Phase 1 offshore wind projects that were unsuccessful in the ORESS 1 capacity auction concluded in June 2023.

IrelandEnergy and Natural Resources

The CRU has published its decision paper on the grid access pathway for Phase 1 offshore wind projects that were unsuccessful in the ORESS 1 capacity auction concluded in June 2023.

ORESS 1

The first offshore renewable electricity support scheme auction (ORESS 1) received submissions from six projects. Of these six submissions, four received a Notice of Award comprising 3,074 MW of awarded capacity. The decision paper concerns the two unsuccessful projects, or 'Merchant Phase 1 Projects', which are the 375 MW 'Oriel' owned by JERA, ESB and Orsted, and the 800 MW 'Arklow Bank 2' owned by SSE (i.e. a further 1,175 MW of offshore generation capacity).

These projects are considered to be well progressed in their development and ability to connect to the grid, as they already possess valid Grid Connection Assessments (GCA) until end of July 2024 and Maritime Area Consents (MAC), these both having been required to participate in ORESS 1.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from