Approach To Support For Offshore Renewable Energy In Ireland

The Timetable, Terms and Conditions and Qualification Information Pack for the first offshore wind renewable electricity support scheme ("ORESS 1") have been published.

IrelandEnergy and Natural Resources

The Timetable, Terms and Conditions and Qualification Information Pack for the first offshore wind renewable electricity support scheme ("ORESS 1") have been published.

Some of the mechanisms proposed for inclusion in the onshore RESS 3 scheme are developed for ORESS 1 - for example, the Unrealised Available Energy Compensation (UAEC), partial indexation, and longer duration of support. We considered these here. While these seek to mitigate some risk for project developers, a degree of uncertainty around compensation for constraints remains.

Projects competing in the ORESS 1 auction are required to have Maritime Area Consents and a Grid Connection Assessment.

Planning Consent (planning permission for the generating plant, offshore grid connection & substation, and onshore grid connection & substation) must be obtained by a Longstop Date of 30 June 2028. Notably however, the Longstop Date may be extended for two years at the Minister's discretion if a Judicial

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This article contains a general summary of developments and is not a complete or definitive statement of the law. Specific legal advice should be obtained where appropriate.