MoRTH Issues Amendments To The Model Concession Agreement For Build Operate Transfer (Toll) Model

JSA Advocates & Solicitors
JSA Advocates & Solicitors
Contributor
JSA Advocates & Solicitors

JSA Advocates & Solicitors

Established in 1991 Our services: JSA is a leading law firm in India with more than 600...

View firm profile
Explore more from JSA Advocates & Solicitors

Some of the amendments which may prove beneficial for concessionaires include introduction of construction support of up to 40% of the Total Project Cost, disallowing the GOI from constructing...

IndiaReal Estate and Construction

Pursuant to extensive deliberations with the implementing agencies and the sector stakeholders, MoRTH issued several amendments to the Model Concession Agreement for Build Operate Transfer (Toll) ("BOT (Toll)") road projects ("MCA") on March 15, 2024. Some of the critical amendments are as follows:

  1. Change in ownership

Earlier, in case of a consortium, each member, whose financial and technical criteria were considered during bid evaluation, was required to hold 26% equity in the concessionaire/ project special purpose vehicle for the construction period and a period of 1 (one) year from the date of completion of Punch List (as defined in the MCA). An amendment is made to the above provision to clarify that each such member must hold: (a) 26% of such equity in the concessionaire which will also not be less than 5% of the Total Project Cost (as defined in the MCA); and (b) this period of 1 (one) year that is computed from the date of completion of the Punch List

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from