Pursuant to extensive deliberations with the implementing
agencies and the sector stakeholders, MoRTH issued several
amendments to the Model Concession Agreement for Build Operate
Transfer (Toll) ("BOT (Toll)") road projects
("MCA") on March 15, 2024. Some of the critical
amendments are as follows:
- Change in ownership
Earlier, in case of a consortium, each member, whose financial
and technical criteria were considered during bid evaluation, was
required to hold 26% equity in the concessionaire/ project special
purpose vehicle for the construction period and a period of 1 (one)
year from the date of completion of Punch List (as defined in the
MCA). An amendment is made to the above provision to clarify that
each such member must hold: (a) 26% of such equity in the
concessionaire which will also not be less than 5% of the Total
Project Cost (as defined in the MCA); and (b) this period of 1
(one) year that is computed from the date of completion of the
Punch List