Developers Cannot Add Floors Without Buyers' Consent- MahaRERA

S.S. Rana & Co.
S.S. Rana & Co.
Contributor
S.S. Rana & Co.

S.S. Rana & Co.

Established in 1989, S.S. Rana & Co. is a premier intellectual property and corporate law firm...

View firm profile
Explore more from S.S. Rana & Co.

The Complainants are allottees in the present case.

IndiaReal Estate and Construction

In a recent development, as reported by the Hindustan Times, the Maharashtra Real Estate Regulatory Authority (MahaRERA) vide its order dated July 30, 2020 in the case of Mr. Deepesh S Singh and ors vs. M/s. Neelkanth Constructions, has directed the Respondent i.e., M/s Neelkanth Constructions to not carry out any construction of extra floors on the project titled 'Neelkanth Vihar Phase I', in the absence of prior approval from the existing buyers1

Brief background

The Complainants are allottees in the present case. The sale agreement was executed between allottees and builder in the year 2017-2018. As per the agreement, possession of the flats had to be given by March 31, 2019 but due to absence of occupancy certificate, the same got delayed. Hence, the possession was granted in the December, 2019 to the Complainants. Thereby, Complainants invoked Section 18 of the Real Estate (Regulation and Development) Act, 2016 asking for interest payment due to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from