No Arbitration Until A Clear Right Is Denied: (Southern Railway v Cherian Varkey Construction Co PVT Ltd

Tuli & Co
Tuli & Co
Contributor
Tuli & Co

Tuli & Co

About us: Tuli & Co was established in 2000 to service the Indian and international insurance and...

View firm profile
Explore more from Tuli & Co

The Division Bench of the Kerala High Court has held that the cause of action giving a party the right to refer a dispute to arbitration only accrues when there is a clear and unequivocal denial of a right asserted by the proposed Respondent.

IndiaLitigation, Mediation & Arbitration

The Division Bench of the Kerala High Court has held that the cause of action giving a party the right to refer a dispute to arbitration only accrues when there is a clear and unequivocal denial of a right asserted by the proposed Respondent.

Facts

Disputes arose between the Southern Railway and its contractor, Cherian Varkey in connection with works for the construction of a bridge. The following timeline is relevant in relation to the facts:

  1. 2008 – Work was completed by the Contractor.
  1. 2010 – The Contractor raised a claim on the Railway for ₹1.19 Crores.
  1. 2012 – The final bill was drawn by the Railway.
  1. 2014 – The Contractor invoked arbitration for the payment of ₹1.19 Crores.