M/s Jindal Steel and Power Ltd. ("Appellant") issued a work order on 24.01.2022 to M/s Bansal Infra Projects Pvt. Ltd. ("Respondent No. 1") for constructing 400 flats at Jindal Nagar...

IndiaLitigation, Mediation & Arbitration

In The Supreme Court of India M/S Jindal Steel and Power Ltd. & Anr. (Appellant) V/S. M/S Bansal Infra Projects Pvt. Ltd. & Others (Respondent)

2025 SCC OnLine SC 1041

Background facts 

  • M/s Jindal Steel and Power Ltd. ("Appellant") issued a work order on 24.01.2022 to M/s Bansal Infra Projects Pvt. Ltd. ("Respondent No. 1") for constructing 400 flats at Jindal Nagar, valued at Rs. 43,99,46,924.13, with an advance of Rs. 3,73,95,490/- secured by a bank guarantee dated 08.03.2022.
  • The project, initially due by September 30, 2022, was extended to 30.06.2023 and later to 30.09.2023 with a condition that retention money would be forfeited if not completed.
  • The Appellant terminated the work order on July 7, 2023, citing Respondent No. 1's poor performance, quality issues, and non-compliance with contract terms. Subsequently, on March 25, 2024, the Appellant demanded Rs. 4,12,54,904/- by 30.04.2024 for unadjusted advances to and encash the bank guarantee

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from