Share on LinkedInShare on LinkedIn

ARTICLE · 05 JUNE 2026

Contract Law May (2026) Contract Law Updates And Judgments

Hammurabi & Solomon Partners
Hammurabi & Solomon Partners
Contributor
Hammurabi & Solomon Partners

Hammurabi & Solomon Partners

With over 100 members in India, Hammurabi & Solomon Partners (H&SP) is the pioneer in the realm of...

View firm profile
Explore more from Hammurabi & Solomon Partners

The petitioner invited an e-tender for the construction of 100 family quarters (Type II, III, and IV), including internal water supply, sanitary installations, and electrical works for the ITBP...

IndiaLitigation, Mediation & Arbitration

NOTABLE JUDGMENTS MAY 2026

1. Proof of Actual Loss Essential: Delhi High Court Sets Aside Damages Award Based on Assumptions

Case Title: Union of India vs M/s Anand & Co. CLICK HERE

Citation: O.M.P. (COMM) 289/2023

Court: High Court of Delhi at New Delhi

Decided on: 04 April 2026

FACTS

The petitioner invited an e-tender for the construction of 100 family quarters (Type II, III, and IV), including internal water supply, sanitary installations, and electrical works for the ITBP 22nd Battalion Campus at Chhawla, New Delhi. The respondent’s bid was accepted, and a Letter of Acceptance dated 20.06.2017 was issued, followed by execution of the agreement. The stipulated date of commencement was 11.07.2017, with a completion period of twelve months, i.e., by 10.07.2018. During execution, disputes arose between the parties, and although the respondent approached the Engineer-in-Charge, no resolution was reached. Clause 25 of the General Conditions of Contract was invoked for

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from