Explore more from Haynes and Boone, L.L.P.

Earlier this month, the English Commercial Court upheld an appeal from an arbitration in MUR Shipping BV v RTI Ltd [2022] EWHC 467 (Comm) that a "reasonable endeavours" requirement...

GlobalInternational Law

Earlier this month, the English Commercial Court upheld an appeal from an arbitration in MUR Shipping BV v RTI Ltd [2022] EWHC 467 (Comm) that a "reasonable endeavours" requirement in a force majeure clause, invoked due to the impact of US sanctions on Russia, did not require the party claiming force majeure to accept non-contractual performance.

Although the case relates to sanctions imposed on Russian entities in 2018, the judgment is duly applicable to the interpretation of force majeure clauses in light of the recent imposition of further sanctions on Russia as a result of the ongoing crisis in Ukraine.

Background of the case

The claim arose out of a dispute between Mur Shipping BV (the "Owners") and RTI Ltd (the "Charterers") in relation to a Contract of Affreightment (the "COA") which the parties entered into in June 2016. Under the COA, the Charterers contracted to ship, and the Owners contracted to carry, approximately 280,000 metric tons per month of