Tender Design To Determine By Auction Feed-In Tariffs For Ground-Mounted Photovoltaic Plants

The act on the fundamental reform of the German Renewable Energy Act was approved by the German Federal Parliament and the Federal Council.

GermanyEnergy and Natural Resources
Hermann Hinderer
Hermann Hinderer

Executive Summary

  • The act on the fundamental reform of the German Renewable Energy Act (EEG 2014) was approved by the German Federal Parliament and the Federal Council. The new EEG will come into force on 1 August 2014.
  • The EEG 2014 paves the way for the shift from statutory feed-in tariffs to determining feed-in tariffs by competitive tenders.
  • As a first step, feed-in tariffs for ground-mounted photovoltaic plants shall be determined by pilot tenders. The transfer of the tendering model to other renewable energies is scheduled for 2017, at the latest.
  • Therefore, the German Federal Government plans to draw up a legislative decree before the end of this year and to organize first tenders during 2015. Key points relating to the tender design have been published by the Federal Ministry of Economic Affairs and Energy ("BMWi") and put to discussion in a consultation process. The deadline for consultation is set for 22 August 2014.