When Applying The Penalty Clause Unjustly Enriches The Owner

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

A Quebec Superior Court decision examines the enforceability of penalty clauses in construction contracts, exploring when courts may reduce stipulated damages that prove abusive despite being contractually agreed upon. The case involves a $30 million wastewater project where 193 days of delays triggered a maximum penalty of nearly $3 million, raising questions about the balance between contractual freedom and good faith requirements.

CanadaReal Estate and Construction

A penalty clause enables a creditor to claim a stipulated penalty without having to prove the injury suffered. In construction contracts, these clauses typically set the damages for project delays in advance.

However, the court retains the power to review and reduce penalties that prove to be abusive. The decision in EBC inc. c. Ville de Montréal, 2026 QCCS 855, illustrates the exercise of this judicial power, which is part of a broader effort to balance freedom of contract with the requirement to act in good faith.

The decision offers an important reminder of the limits of penalty clauses in construction law and the circumstances in which a clause may be considered abusive.

Where the delays are significant, so is the penalty

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from