On March 24, 2020, the Government of Quebec announced the
suspension of all construction projects underway in Quebec except
those related to the performance of "priority" services
due to the global COVID-19 pandemic.
This suspension is likely to result in significant costs for the
various stakeholders involved in the construction sector. These
costs include those associated with delays in the work, the
dismantling of construction sites, the storage of materials and
machinery and the supervision of sites during the suspension.
The reopening of all construction sites announced on April 28,
2020, by the Québec Government could also result in
significant costs. In addition to the cost of restarting projects
significant financial resources will have to be allocated for the
implementation of the health measures required by the Commission
des normes, de l'équité, de la santé et de
la sécurité du travail (CNESST). It is also likely
that the cost of certain materials will