The projected start date is often a determining factor in a
bidder's estimate of the contract price.
It is often advantageous for a bidder to plan for the work to be
completed during the mild season, or for the buildings to be shut,
in order to minimize the cost of enclosures, snow removal, heating
and the loss of productivity associated with performing certain
kinds of work in winter, not to mention the suspension of work
during statutory holidays.
According to principles well established by the courts in such
decisions as Construction BSL Inc. v.
Ste-Agathe-de-Lotbinière (Municipalité de),
EYB 2009-153544 (C.A.), a bidder cannot presume that the desired
contract will be awarded before the bid cut-off date, except in
special circumstances, namely when information to the contrary is
received from the awarding authority or one of its
representatives.