New Year, New Rules: Construction Act Amendments Explained

Gardiner Roberts LLP
Gardiner Roberts LLP
Contributor
Explore more from Gardiner Roberts LLP

Several amendments to the Ontario Construction Act (the "Act") came into force on January 1, 2026, pursuant to Bill 216, Building Ontario For You Act, and Bill 60, Fighting Delays, Building Fact Act.

CanadaReal Estate and Construction

Several amendments to the Ontario Construction Act (the "Act") came into force on January 1, 2026, pursuant to Bill 216, Building Ontario For You Act, and Bill 60, Fighting Delays, Building Fact Act. These amendments include changes to the definitions, prompt payment provisions, adjudication process and most impactful, mandatory annual holdback releases. We highlight a few of the notable changes that developers, owners, contractors and subcontractors should be aware of.

New Mandatory Annual Releases from Holdbacks

Sections 26, 26.1, 26.2, 27 and 27.1 of the Act have been repealed and replaced with a new framework governing holdback payments. There are now mandatory annual holdback payments for owners, contractors and subcontractors. The following process is to be followed:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from