Share on LinkedInShare on LinkedIn

ARTICLE · 23 FEBRUARY 2018

Mitigate Before You Litigate: Recovering Damages For Renovations Gone Wrong

The Court will not always resolve a construction contract dispute against a contractor who clearly provided deficient work.

CanadaReal Estate and Construction

The Court will not always resolve a construction contract dispute against a contractor who clearly provided deficient work. If you have been wronged by a residential renovation that's gone off the rails, or if you're a contractor and a client is refusing to pay based on this premise, it is important to first understand what kind of contract you have, and whether the alleged breach goes to the root of the contract. Whether you have done wrong or been wronged, Field Law can help you through this process.

Look to the Nature of the Contract

In the recent decision of 1314058 Alberta Ltd v Albers, 2018 ABQB 9, the Court considered whether victims of a "residential renovation gone wrong" could collect from their contractor for his admittedly faulty work. In this case, the Defendants hired the Plaintiff to renovate their newly purchased home. The Defendants accepted a fixed-price quote. After two months, the work stopped based on issues with the workmanship. By then, the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.