For commercial real estate lenders, advancing loan funds safely requires ensuring that no active construction liens can impact the property. This is crucial in mitigating financial risks associated with construction projects.

CanadaReal Estate and Construction

For commercial real estate lenders, advancing loan funds safely requires ensuring that no active construction liens can impact the property. This is crucial in mitigating financial risks associated with construction projects. The construction lien regime in Ontario is governed by the Construction Act, R.S.O. 1990, c. C.30, which provides clear guidelines on the lien period. Understanding and determining if the construction lien period has expired is essential for lenders.

Key Statutory Provisions

  1. Lien Period: According to Section 31 of the Act, a lien must be preserved within 60 days after the date of the last supply of services or materials to the improvement. If the lien is not preserved within this period, it expires and can no longer be enforced.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.