Development Charge Credit Claims

In P. Barnett Construction v. Burlington (City), (2008), 44 M.P.L.R. (4th) 122, the Ontario Superior Court of Justice dismissed an application by a landowner seeking an exemption from development charges (DCs) by virtue of subdivision (lot levy) agreements that had been entered into.

CanadaReal Estate and Construction

Introduction

In P. Barnett Construction v. Burlington (City), (2008), 44 M.P.L.R. (4th) 122, the Ontario Superior Court of Justice dismissed an application by a landowner seeking an exemption from development charges ("DCs") by virtue of subdivision (lot levy) agreements that had been entered into.

The subdivision agreements in this case dated back to the 1980s and provided for lot levies to be collected by the City of Burlington ("Burlington"). The levies were applied to all non-residential development in Burlington and were adopted by Burlington as policy, in effect as of the time of the execution of the subdivision agreements.

In 1989, the Province of Ontario enacted the Development Charges Act, 1989 ("Old DCA") which replaced the lot levy regime with development charges ("DCs"). Municipalities were empowered to impose DCs pursuant to development charge by-laws enacted under the Old DCA. The Old DCA did not exempt from the payment of DCs those lands that were