Homeowners sought to remove a mechanics' lien filed by their contractor for renovation work, arguing that the lien was registered and perfected outside the statutory limit.

CanadaReal Estate and Construction

Homeowners sought to remove a mechanics' lien filed by their contractor for renovation work, arguing that the lien was registered and perfected outside the statutory limit. The Court dismissed the homeowners' application to vacate the lien at this preliminary stage, citing significant factual disputes regarding the true last date of supply that necessitate a trial for resolution. This decision underscores the importance of precise documentation relating to the last date of supply, and highlights how the court will treat cases where the last date of supply is unclear.

In January 2023, the Applicants - Environmental Applications Group Inc., along with individuals Giovanni Sferrazza and Michelle Murray - contracted with Sam Design to renovate and decorate their home. By August 2023, Sam Design said it had completed 90% of the project and requested final payment. Disagreements arose over unpaid balances, work deficiencies, and whether certain tasks remained undone.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.