The line between what work gives rise to a valid builders' lien, and that which doesn't, can be blurry.

CanadaReal Estate and Construction

The line between what work gives rise to a valid builders' lien, and that which doesn't, can be blurry. The recent decision of YoungEnergyServe Inc. v LR Ltd, LR Processing Partnership, 2021 ABQB 101, has set out a framework for determining when a builders' lien is valid.

In that case, YESCo contracted with LR to clean, repair, and reline the interior of all of the tanks and pressure vessels at LR's Mazeppa Gas Plant in High River. YESCo alleged that it was owed $1.7 million for its work, registered and filed a builders' lien against LR's lands. The Court ruled that the lien was invalid.

Builder's Liens Must be an "Improvement"

The validity of YESCo's lien depended on whether its work was done in respect of an "improvement" or was simply maintenance.  Section 6 of the Builders' Lien Act (the BLA) entitles a person to a lien where that person has worked on or contributed material in respect of an "improvement" on that land.  Section 1 of the BLA defines

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from