Share on LinkedInShare on LinkedIn

ARTICLE · 08 MAY 2020

Time's Up – Appeal Court Confirms Strict Time Limits For Construction Claims

MLT Aikins LLP
MLT Aikins LLP
Contributor
MLT Aikins LLP

MLT Aikins LLP

FIRM OVERVIEW MLT Aikins is a full-service business law firm of more than 375 lawyers with a deep...

View firm profile
Explore more from MLT Aikins LLP

The Saskatchewan Court of Appeal recently released a decision dealing with statutorily imposed deadlines for commencing lawsuits in Saskatchewan.

CanadaLitigation, Mediation & Arbitration

The Saskatchewan Court of Appeal recently released a decision dealing with statutorily imposed deadlines for commencing lawsuits in Saskatchewan. This decision will directly impact when a party must commence a lawsuit, particularly in the context of disputes arising during long-term construction projects.

In Saskatchewan (Highways and Infrastructure) v Venture Construction Inc., 2020 SKCA 39 [Venture Construction], the Saskatchewan Court of Appeal reversed a lower court decision on a limitations period issue, concerning whether a claim had been brought in time.

Background

The specific facts of the case were fairly straightforward:

  • Venture Construction contracted to perform road construction for the Ministry of Highways.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from