In Center Street Limited Partnership v. Nuera Platinum Construction Ltd, 2025 ABCA 290, the Alberta Court of Appeal was asked to consider the impacts of a standstill agreement and coverage action on the "main" action.

CanadaLitigation, Mediation & Arbitration

In Center Street Limited Partnership v. Nuera Platinum Construction Ltd, 2025 ABCA 290, the Alberta Court of Appeal was asked to consider the impacts of a standstill agreement and coverage action on the "main" action.

Facts

On March 7, 2025, a fire broke out on the roof of a commercial building owned by Center Street Partnership (Center Street).

Construction was underway at the time, with Neura Platinum (Neura) managing the project, and Over & Above Reno and Contracting in charge of roofing and waterproofing. Center Street commenced both an action against the construction companies for negligence and breach of contract (trades action), and a claim against the insurer after a denial of coverage (coverage action).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from