Construction disputes are often comprised of competing claims
for delay, non-payment, deficiencies, and the like. Where one party
to the dispute pleads set-off or mutual debts, it can prevent a
party from achieving what would otherwise be a speedy resolution
through summary proceedings. This can be frustrating for the other
party who may feel their claim is simple; for example, in cases of
non-payment under a written contract where the work has been
clearly performed.
In Tempo Alberta Electrical Contractors Co Ltd v
Man-Shield (Alta) Construction Inc., 2025 ABCA 310
(“Tempo v Man-Shield”) the
Alberta Court of Appeal clarified that the defence of equitable set
-off is a true defence that can give rise to a genuine issue
requiring a trial, thereby precluding the ability to obtain a quick
judgment through summary proceedings.