ARTICLE · 30 AUGUST 2019

English Commercial Court Enforces Multi-Billion Arbitral Award Over Failed Gas Project

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

On August 16, 2019, the England and Wales High Court of Justice (Commercial Court) released its decision in Process & Industrial Developments Limited v The Federal Republic of Nigeria

CanadaLitigation, Mediation & Arbitration

On August 16, 2019, the England and Wales High Court of Justice (Commercial Court) released its decision in Process & Industrial Developments Limited v The Federal Republic of Nigeria ("Process & Industrial Developments"), [2019] EWHC 2241, in which it enforced a US$9 billion arbitral award against the Republic of Nigeria ("Nigeria"). The enforcement of this 'mega-award' is significant for oil and gas companies doing business abroad and also for the practice of international commercial arbitration.

The Decision

Process & Industrial Developments Ltd. ("PID"), a BVI entity, entered a "Gas Supply and Processing Agreement" with Nigeria (the "Agreement"). Under the Agreement, PID was to build and operate a gas processing plant for "wet gas" to be supplied from the Nigerian Ministry of Petroleum Resources. The Agreement had a 20 year term. Furthermore, the Agreement contained an arbitration clause, which stated:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.