Share on LinkedInShare on LinkedIn

ARTICLE · 07 DECEMBER 2021

The Importance Of Consultation With First Nations, Progressive Reclamation And Increased Reclamation Security For Amended Permits In The Mining Industry

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

The BC Supreme Court recently cast light on issues regarding British Columbia mining operations on First Nation's territory in Ignace v. British Columbia (Chief Inspector of Mines), 2021 BCSC 1989.

CanadaGovernment, Public Sector

The BC Supreme Court recently cast light on issues regarding British Columbia mining operations on First Nation's territory in Ignace v. British Columbia (Chief Inspector of Mines), 2021 BCSC 1989. Miller Thomson was counsel in Ignace challenging the permit amendment.

The Court determined that the decision by the Inspector of Mines (the "Inspector") to issue an amended permit in 2019 (the "Amended Permit") under the Mines Act, increasing production in the McAbee Quarry (the "Quarry"), was unreasonable and failed to adequately discharge the honour of the Crown regarding the consultation process with the Stk'emlupsemc te Secwepemc Nation ("SSN").

Notably, the Court also ventured into relatively uncharted waters for a long-standing mining operation in finding the Inspector's decision unreasonable on the grounds that:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from