ARTICLE · 17 JANUARY 2014

Province Ordered To Pay Damages To Timber Company Over Aboriginal Road Blockade

On December 23, 2013, the British Columbia Supreme Court ordered the Province of British Columbia to pay logging contractor Moulton Contracting Ltd. a sum of $1.75 million in damages for the Province’s failure to warn Moulton Contracting of an imminent blockade by members of the Fort Nelson First Nation.

CanadaGovernment, Public Sector

On December 23, 2013, the British Columbia Supreme Court (Court) ordered the Province of British Columbia (Province) to pay logging contractor Moulton Contracting Ltd. a sum of $1.75 million in damages for the Province's failure to warn Moulton Contracting of an imminent blockade by members of the Fort Nelson First Nation (FNFN). The blockade occurred on a Moulton Contracting access road that prevented Moulton Contracting from carrying out logging activity.

This decision follows seven years of legal proceedings, including a Supreme Court of Canada decision on May 9, 2013. The SCC held that FNFN members could not raise an alleged breach of the duty to consult treaty rights as a defence against Moulton Contracting's tort action arising from a blockade without challenging the licences in question.1

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from