ARTICLE · 17 FEBRUARY 2026

Manitoba Hydro's 2025 Integrated Resource Plan: New Wind Power Remains Key Component Of Province's Future Energy Mix

In our January 2026 blog: Manitoba Call for Power: update on procurement process for Indigenous majority-owned wind projects, we outlined Manitoba Hydro's progress in its procurement process for up to 600 megawatts (MW)...

CanadaGovernment, Public Sector

Key takeaways

  • Manitoba Hydro plans to add 1,760 MW of accredited electricity capacity by 2035, including 600 MW of new wind power and 750 MW of gas-fired generation.
  • The 2025 Integrated Resource Plan (IRP) outlines two development scenarios: a recommended plan and an alternative plan, each with varying resource allocations.
  • The IRP highlights the critical role of new wind power in Manitoba's long-term energy strategy.

Overview

In our January 2026 blog: Manitoba Call for Power: update on procurement process for Indigenous majority-owned wind projects, we outlined Manitoba Hydro's progress in its procurement process for up to 600 megawatts (MW) of Indigenous majority-owned wind power. On February 2, Manitoba Hydro announced that it filed its 2025 Integrated Resource Plan (IRP) [PDF] with the Manitoba Public Utilities Board.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from