Legal Basics Of Procurement – Part 2 (Duty Of Good Faith)

Alexander Holburn Beaudin + Lang LLP
Explore more from Alexander Holburn Beaudin + Lang LLP

The following article discusses the differences between traditional tendering contracts and request for proposals (or RFPs), in relation to the duty of good faith.

CanadaGovernment, Public Sector

The following article discusses the differences between traditional tendering contracts and request for proposals (or RFPs), in relation to the duty of good faith.

1. What is an invitation to tender?

The formative Canadian decision on the tendering process and competitive bidding in Canada is the Supreme Court of Canada decision in Queen (Ontario) v. Ron Engineering & Construction (Eastern) Ltd., (1981) 1 S.C.R 111 ("Ron Engineering").

Before Ron Engineering, the law surrounding an invitation to tender was very different. A tenderer could withdraw its tender at any time prior to the acceptance of bids, as the act of bidding was seen as a non-binding negotiation rather than the acceptance of a contract. The decision in Ron Engineering changed this by adopting a Contract A/Contract B analysis in the tendering context. Contract A is created when a tenderer responds with a compliant offer to an invitation to tender. Upon the acceptance of a tender, a second contract