BACKGROUND
The West Moberly First Nations were unsuccessful on October 24,
2018 (see 2018, BCSC 1835) in obtaining an injunction against B.C.
Hydro and Power Authority from further construction and related
activities on the Site C Project. The project consists of a
hydroelectric dam, generating station and associated infrastructure
including, the widening of an existing transmission line and the
realignment of a highway along the Peace River in northeastern B.C.
The primary relief sought was to enjoin work for 24 months or
pending final determination of their claim, whichever came earlier,
except for such measures as Hydro and the regulators determined to
be necessary to ensure safety, prevent environmental harm and
preserve, maintain and care for the work product already done.
Alternatively, the First Nation sought to prohibit work during this
period in 13 critical areas of particular importance to the
exercise of their rights under Treaty 8. That concession