The Ontario Environmental Review Tribunal (the ERT) released its landmark ruling in the wind farm challenge case, Erickson v. Director, Ministry of the Environment (Erickson) on July 18, 2011.

CanadaEnvironment

The Ontario Environmental Review Tribunal (the ERT) released its landmark ruling in the wind farm challenge case, Erickson v. Director, Ministry of the Environment (Erickson) on July 18, 2011. It is the first ERT decision addressing an appeal from the issuance of a Renewable Energy Approval (REA). This decision is important since it shows that the ERT is willing to strictly apply the wording of section 145.2.1(2) of the Environmental Protection Act (EPA) in deciding appeals from the issuance of REAs.

The applicant, Suncor Energy Services Inc. (Suncor), applied for and was granted an REA under section 47.5 of the EPA for eight wind turbines to be developed at a facility to be known as Kent Breeze Wind Farms, located in the Township of Camden, Ontario (the Project) by the Director, Ministry of the Environment (the Director). Local residents groups and a local resident (the Appellants) appealed the decision to the ERT. The ERT dismissed the appeal by the Appellants, but

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from